Project Planning
Week 3 -- Planning Proposal and Discuss The layout of Website
Week 4 -- Scheduling time for getting information and start gather information ( Duration 2 weeks )
Week 6 -- Reorganization Information and Learning using WAMP (Duration 2 weeks)
Week 8 -- Construct Database and PHP Coding (Duration 2Weeks)
Week 10 -- Testing & re-discuss and debugging (Duration 2Weeks)
Week 12 -- Doing Extra Feature
Edited Proposal
Objective:
To Provide Cafe and Restaurant Information for users
Features:
-User Register
-User Login
-Adding post
-edit post
-delete post
-keyword search
-criteria search
-Admin maintainance
-Upload photo
To Provide Cafe and Restaurant Information for users
Features:
-User Register
-User Login
-Adding post
-edit post
-delete post
-keyword search
-criteria search
-Admin maintainance
-Upload photo
Sunday, March 1, 2009
The first Process
We have decide base of our web application and the way we going to do. so we have target some area of the restaurant and cafe near MMU for advertise in our web application. We also will ask and give the form for them to collect some data we need to shown in web.
After we collect all the data we needed, then we will starting to do and design our web advertisement.
After we collect all the data we needed, then we will starting to do and design our web advertisement.